4.3 Procurement planning and selection of method
Procurement begins with a real, budgeted and specified need, not with a preferred supplier. The planning record should answer:
| Question | Evidence | |---|---| | What is needed? | Clear scope, specification or terms of reference, and quantity. | | Why is it needed? | Link to an approved function, project or service. | | Is funding available? | Correct provision and timing. | | Which method applies? | The current threshold, the nature of the requirement, the market and a rule-based justification. | | When is it needed? | A realistic procurement and delivery schedule. | | Who is responsible? | Named officers, committees and milestones. |
A requirement must not be divided artificially to fall below an approval or procurement threshold. The genuine requirement is analysed as a whole and the current rules are applied to it. Splitting a purchase to avoid a control is itself a procurement irregularity.
*Anchors: FR 716, 717; Procurement Guidelines 2024 (document level).*