F.R. 66 Transfer of Financial Provision – Virement Procedure

(1) When the financial provision appropriated in the Estimates to any Programme, Project, Object Class, or Item of a Head of Expenditure is found to be inadequate for expenditure during the financial year and is likely to exceeded, and if the relevant Account Officer and Chief Account Officer are satisfied with regard to the necessity for additional financial provision, savings, which are likely to be available during the financial year, under any other Programme, Project, Object Class, or Item of the same Head of Expenditure may, subject to FR 65, be transferred to cover such anticipated excess expenditure in the manner specified below. No such excess expenditure should be incurred until such transfer is authorized by the appropriate authority.

(2) Transfer between Programmes:

(a) Capital Expenditure : It should be clearly understood that provision cannot be transferred out of the capital expenditure component of any Programme under which it is provided.

(b) Recurrent Expenditure : Transfer of savings from a recurrent expenditure provision of any Programme under any Head of Expenditure to the capital expenditure provision of the same Programme or to the recurrent expenditure provision or capital expenditure provision of any other Programme under the same Head of expenditure should be ordered by the Secretary to the Treasury or any other officer authorized by him as provided for in the Appropriation Act. Transfers between Programmes can be done only if the Appropriation Act provides for such transfers.

(c) Applications : Applications for transfer in respect of this sub- section should be forwarded to reach the Director General of National Budget in sextuplicate on form General 271 before the 31<sup>st</sup> December of the financial year.

(3) Transfer between Projects of a Programme:

(a) Capital Expenditure: Transfer of financial provision between capital expenditure Projects of a Programme should be authorized by the Secretary to the Treasury/Deputy Secretary to the Treasury or any other officer authorized by Secretary to the Treasury.

(b) Recurrent Expenditure : Transfer of financial provision between recurrent expenditure Projects of a Programme should be authorized by the Secretary to the Treasury /Deputy Secretary to the Treasury or any other officer authorized by Secretary to the Treasury.

(c) Applications : Applications for transfers in respect of (a) and (b) above should be forwarded to reach Director General of National Budget in sextuplicate on form General 233 before the 31<sup>st</sup> December of the financial year.

(4) Transfer between Object Classes of a Project :

(a) Capital Expenditure : Transfer of financial provision between Object Classes of a Capital expenditure Projects should be authorized by the Secretary to the Treasury/Deputy Secretary to the Treasury or any other officer authorized by Secretary to the Treasury.

(b) Recurrent Expenditure : Transfer of financial provision between Object Classes of a recurrent expenditure Projects should be authorized by the Secretary to the Ministry concerned/ Chief Accounting Officer.

(c) Applications : Applications for transfers in respect of (a) and (b) above should be forwarded to respective authorities in sextuplicate on Form General 233 on or before the 31<sup>st</sup> December of the financial year.

(5) Transfer between controlled Items of a Project :

(a) Capital Expenditure : Transfer of financial provision between controlled/ Items of expenditure projects should be authorized by the Secretary to the Treasury/Deputy Secretary to the Treasury or any other officer authorized by the Secretary to the Treasury,

(b) Recurrent Expenditure: Transfer of financial provision between controlled/Items of a recurrent expenditure projects should be authorized by the Head of Department/ Accounting Officer.

(c) Applications : Applications for transfers in respect of (a) and (b) above should be forwarded to respective authorities in sextuplicate on Form General 233 on or before the 31<sup>st</sup> December of the financial year.

(6) Figures of Expenditure to be furnished in application: In every application for transfer the financial provision allocated in the Estimates, the actual expenditure to the latest date for which figures are available, the anticipated expenditure for the rest of the financial year and the additional financial provision required or anticipated savings under each Object Detail/Item involved in the transfer should be clearly indicated.

(7) Adjustment of provision to be noted in the Appropriation (Votes) Ledgers: In order to ensure that the authorized financial provision under the Programme, Project, Object Class, or Item is not exceeded the transfer of provision should be noted in the Appropriation (Votes) Ledgers after the necessary authority for such transfer has been granted.

(No F.R. Issued Under No.67)