CHAPTER I

ESTIMATES OF EXPENDITURE AND REVENUE PAGE THE CONSOLIDATED FUND AND PLANNING AND PROGRAMMING OF EXPENDITURE Section 1 - … FORM OF PRESENTATION OF ANNUAL ESTIMATES OF EXPENDITURE … NEW PROPOSALS Section 2 - Section 3 - … PREPARATION, SUBMISSION AND PASSING OF ESTIMATES OF EXPENDITURE Section 4 - … VARIATIONS TO ESTIMATES OF EXPENDITURE ESTIMATES OF REVENUE Section 5 - … Section 6 - … CHAPTER 1

ESTIMATES OF EXPENDITURE AND REVENUE

Section 1 — The Consolidated Fund and Planning And Programming of Expenditure

Section 1 - The Consolidated Fund and Planning And Programming of Expenditure

F.R.1. Financial Year. The Financial Year of the Republic commences on the 1st of January of each year and ends on the 31st of December of the same year.

F.R.2. (1) Provision in the Constitution. The following Articles of the Constitution of the Democratic Socialist Republic of Sri Lanka, 1978, relating to payments into the Consolidated Fund and withdrawals from the Fund are reproduced here for the information and guidance of officers:- Article 148. Parliament shall have full control over public finance. No tax, rate or any other levy shall be imposed by any local authority or any other public authority, except by or under the authority of a law passed by Parliament or of any existing law. Article 149.(1) The funds of the Republic not allocated by law to specific purposes shall form one Consolidated Fund into which shall be paid the produce of all taxes, imposts, rates and duties and all other revenues and receipts of the Republic not allocated to specific purposes.

(2) The interest on the public debt, sinking fund payments, the costs, charges and expenses incidental to the collection, management and receipt of the Consolidated Fund and such other expenditure as Parliament may determine shall be charged on the Consolidated Fund. Article 150. (1) Save as otherwise expressly provided in paragraphs(3) and (4) of this Article, no sum shall be withdrawn from the Consolidated Fund except under the authority of a warrant under the hand of the Minister in charge of the subject of Finance.

(2) No such warrant shall be issued unless the sum has by resolution of Parliament or by any Law been granted for specified public services for the financial year during which the withdrawal is to take place or is otherwise lawfully charged on the Consolidated Fund.

(3) Where the President dissolves Parliament before the Appropriation Bill for the financial year has passed into law, he may, unless Parliament shall have already made provision, authorize the issue from the Consolidated Fund and the expenditure of such sums as he may consider necessary for the public services until the expiry of a period of three months from the date on which the new Parliament is summoned to meet.

(4) Where the President dissolves Parliament and fixes a date or dates for a General Election the President may, unless Parliament has already made provision in that behalf, authorize the issue from the Consolidated Fund and the expenditure of such sums as he may, after consultation with the Commissioner of Elections, consider necessary for such elections. Article 151 (1) Notwithstanding any of the provisions of Article 149, Parliament may by law create a Contingencies Fund for the purpose of providing for urgent and unforeseen expenditure.

(2) The Minister in charge of the subject of Finance, if satisfied -

(a) that there is need for any such expenditure, and

(3) As soon as possible after every such advance, a Supplementary Estimate shall be presented to Parliament for the purpose of replacing the amount so advanced. Article 152. No Bill or motion, authorizing the disposal of, or the imposition of charges upon, the Consolidated Fund or other fund of the Republic, or the imposition of any tax or the repeal, augmentation or reduction of any tax for the time being in force shall be introduced in Parliament except by a Minister, and unless such Bill or motion has been approved either by the Cabinet of Ministers or in such manner as the Cabinet of Ministers may authorize.

(2) Monies in the Consolidated Fund.

(a) The consolidated Fund comprises all monies belonging to the Republic which are not separately allocated to other specific funds.

(b) The Fund also comprises monies ( including money in bank accounts) of the various departments and funds of the Republic with the Crown Agents and other Approved Overseas Agents of the Republic and also includes investments.

(3) Expenditure from the Consolidated Fund. Provision for expenditure from the Consolidated Fund, falls into two main categories - (I ) Supply Services. Supply Services are services for which appropriations are made by an Appropriation Act or by a Resolution in Parliament or by authority issued in terms of Article 150 (3) and Article 150 (4) of the Constitution. (ii) Special Law Services. Special Law Services are those for which provision is made by specific provisions of the Constitution or by any other Law than those referred to in sub-section (i) above.

(4) Special Statutory Funds. ( i) Another source of funding activities of Government are special Funds created by statutes enacted by Parliament. Law prescribes how monies are collected for such Funds and how Funds should be disbursed out of such Funds. Such Funds are not included in the General Estimates. Any provision in the Annual Estimates for those Funds would be by way of Contributions or Grants, under the respective Heads and Programmes. (ii) Corporate Plans and the Annual Budget of such Funds should be forwarded to the National Planning Department and Public Enterprises Department or the Department of Public Finance of the Treasury for approval. (iii) If Budgetary support is sought for such Funds, copies of the annual budget Indicating the purpose and the amount of budgetary support should be forwarded to the Director General of National Budget of the General Treasury along with reasons to justify such support.

(5) Advance Accounts Activities. Certain activities of government are financed by way of Advance Accounts. Appropriations for Advance Account Activities are made separate from the General Estimates and form a separate Fund for each activity. Budget for each activity should be prepared separately and accounts be kept separately. Advance Account Activities are grouped under the relevant Heads of Expenditure. Coding for identification purposes is done with five digit numbers. The first three digits being the Head number of the Ministry or Department under which the activity is carried out.

F.R.3. Planning of Expenditure. (1) All activities of government should be pre-determined and set out in Plans and Programmes. The annual estimates of expenditure for a particular financial year are the financial expression of the Government’s Programmes of activity during such year. Plans and programmes are composed of projects. The incorporation of Capital Projects in the Annual Estimates of Expenditure will be on the basis of the Public Investment Programme where allocations will be indicated under two categories namely ongoing ( Continuation) and New Projects.

(2) Project Planning and the Two Staged Approval Procedure (i) For the purpose of planning and approval, projects are classed into-

(a) Sectoral Plans Sectoral Plans are multi year ( normally 5 years) programmes of a particular sector. They are prepared by the line Ministries or Departments, in consultation with and with the assistance of the National Planning Department and should be included in the Two-Stage Procedure. Such Plans will normally form the basis for identification of new projects, ( many or which may, in themselves be quite small) and should therefore be submitted for Preliminary Approval to the Cabinet of Ministers through the National Planning Department and the Committee of Development Secretaries.

(b) Large Projects A large project is one the initial cost of which is not less than Rs. 10,000,000 and the recurrent annual operation and maintenance cost exceeds Rs, 500,000. Such projects should pass through the full two stage procedure. However, in the case of large projects which are parts of a Sectoral Plan or Programme and have received preliminary approval of the Cabinet during the last five years, such projects will be accepted as having received the preliminary approval. The National Planning Department and the Central Environment Authority should however be informed and comments be obtained before detailed formulation of the projects commences.

(c) Small Projects Small Projects are defined as projects with a capital cost less than Rs.10,000,000 and a recurrent operation and maintenance cost less than Rs. 500,000 per annum. It is not permitted to break down a project into separate components in order to classify it as a small project. Small projects need not pass through both stages of the two-stage procedure if the project is not part of an approved sectoral Plan or Programme. It must be submitted for preliminary approval to the Committee of Development Secretaries in the usual manner. Once such approval has been granted the project will be included in the Public Investment Programme. (ii) Project Planning should pass through the following stages:- (a) Identification (b) Preliminary Appraisal (c) Preliminary Approval (Approval-in-Principle) (d) Preparation (e) Full Appraisal (f) Final Approval ( Final Round Approval) (g) Inclusion in the Public Investment Programme (h) Incorporation into the Budget (i) Implementation (j) Evaluation (iii) Two Stage Approval Procedure Two Stage Approval Procedure of Projects consists of Preliminary Approval and Final Approval.

(a) The relevant Department or Public Institution shall identify the project and prepare a Pre-Feasibility report with the assistance of the possible Aid Donors and submit it to the Sponsoring Ministry.

(b) The Sponsoring Ministry if accepted will submit the project in the Preliminary Approval form to the National Planning Department and the Committee of Development Secretaries.

(c) National Planning Department will do a preliminary appraisal and report to the Committee of Development Secretaries.

(d) Committee of Development Secretaries, if necessary, in consultation with the other Ministries recommends the project to the Cabinet for Preliminary Approval.

(e) When the preliminary Approval is granted by the Cabinet, the pre-Feasibility report of the project is passed on to the Sponsoring Ministry and if necessary to the External Resources Department.

(f) Then the Sponsoring Ministry along with Department/Public Institution should do a feasibility study, formulate the project with the assistance of the possible aid donors and in consultation with the Inter-Disciplinary Committee, if any; and submit it to the Committee of Development Secretaries in the Final Approval Form.

(g) National Planning Department will do the final appraisal of the project and report to the Committee of Development Secretaries.

(h) The Committee of Development Secretaries will consider the Project Proposal along with the Final Appraisal Report and in consultation with other relevant Ministries and recommend to the Cabinet who will grant the Final Approval.

(iv) Planning Unit A Planning Unit should be set up in each Ministry. The main functions of the Planning Unit shall be :-

(a) Preparation, revision and implementation of long and medium-term sectoral plans, the setting of objectives and strategies, and co-ordination with the National Planning Department on sectoral planning ;

(b) Identification and preparation of new projects within the framework of sectoral plans, and their economic appraisal and environmental assessment;

(c) Consideration of all types of economic policies and their social implications within the framework of sectoral plans and objectives, including (as appropriate) prices,subsidies,transfer payments,etc;

(d) Consideration of the social impact of sectoral plans and projects on local populations ;

(e) Co-ordination with the ministry’s finance officer on the preparation of budget estimates in line with the ministry’s long and medium-term objectives and the target figures in the Public Investment Programme, and joint consideration of these estimates with the Department of National Budget ;

(f) Monitoring of project and plan progress, identification of problems, and initiation of remedial action in the event of delays ; Co-ordination with the Progress Control Division of the Ministry of Plan Implementation ;

(g) Co-ordination of the Ministry’s activities at the subnational level, including District and other local planning units, and with District-level plans ;

(h) Since adequate data are essential for all forms of planning, the creation of a sound statistical base is also necessary, in liaison with the Department of Census and Statistics ;

(i) Keeping up-to-date with international and national developments in that sector, including research in Sri Lanka and elsewhere, and advising on its implications ;

(j) Advising the Secretary on all aspects of sectoral and project planning and economic and social performance.

F.R.4 The Programming of Expenditure. (1) It is the responsibility of the Chief Accounting Officer and the Accounting Officer to ensure that the funds to be authorized by Parliament in the Annual Estimates is restricted to the programme of work that can be achieved during the financial year.

(2) The Programming for Implementation should normally be done when projects are formulated. In any case it should be done before the financial year of expenditure commences. No financial commitment or liability should be incurred until the relevant warrant is issued. ( see FR 90) (3) Feasibility studies regarding recurrent expenditure should be under-taken and expenditure forecasted before budgeting. Targets, output and objectives of recurrent expenditure should clearly be defined to restrain undue expansion of expenditure. Ways and means of eliminating waste and effecting strict economics should be adopted. Organization should be structured to ensure closer monitoring and accountability. For this purpose each project and object class may be divided into suitable smaller units or components.

(4) When the capital projects are duly approved, the implementing agency should prepare the detailed Total Cost Estimate indicating the sources of financing and also draw up a programme of implementation indicating the time span. Each project and object class may be broken into items, works, tasks, activities or any other convenient cost units to facilitate monitoring and progress control. A suitable technique like the Network Analysis may be used for the implementation programme.

(5) A Progress/Monitoring committee should be set up in each implementing agency to ensure that the output is achieved as programmed. For this purpose, the committee should among other things:-

(a) maintain a detailed breakdown of the projects into items of work, tasks, activities etc.

(b) record progress according to predetermined target dates.

(c) Attempt to identify constraints relating to materials, personnel or organization which may delay progress and take timely remedial action. The progressive compilation of work-norms and the formulation of units costs will also be an important part of the Committee’s duties. The committee shall report regularly to the Accounting Officer and the Chief Accounting Officer. When other departments are involved in the completion of particular aspects of departmental projects, officers of such other departments may also be co-opted as members of the Committee. This should be done in consultation with the Secretaries concerned.

(6) The Chief Accounting Officer should exercise general supervision over the detailed programming of expenditure and should wherever necessary, co-ordinate the activities of the several departments under his control.

(No F.R. issued under number 5 )

Section 2 — Form of Presentation of Annual Estimates

Section 2 – Form of Presentation of Annual Estimates

F.R. 6 Publications

(1) Estimates of Revenue and Expenditure of Government for the Financial year shall include :- (a) Estimates of Revenue (b) General Estimates of Expenditure (c) Estimates relating to Advance Accounts (d) Salary Scales of the Public Service

(2) Detailed Staff Schedule This is published separately and shall include information regarding all cadres in Group B – Staff Officers, Group C – Sub-ordinate Officers and Group D – Minor Grade Officers under each Project in each Programme of Expenditure. The Schedule should include-(a) Group of Officers and the Posts

(b) Salary Scale (c) Actual number of Permanent/Temporary or Casual Officers at the end of previous year and the total salary paid during the year (d) Estimated number and salary of Permanent/Temporary or Casual Officers for the current year. (e) Estimated number and salary of Permanent/ Temporary or Casual Officers for the ensuing year.

(3) Summary of Income and Expenditure This is published in addition the detailed Estimates of Revenue and Expenditure and include summary of receipts of the government, summary of actual expenditure of the government for the previous year and the estimates of expenditure for the current year and the budget year. Expenditure figures are shown by Head, Programme and Project.The summary of Expenditure by Departments, functions, economic line items are also included in this publication.

(4) Form of Estimates of Expenditure Estimates of Expenditure Published as an appendix to the Annual Appropriation Act is composed of :-

(a) Part I – General Estimates - General Estimates consist of budgetary provisions made under Schedule 1 of the Appropriation Act and the annual appropriations under special Laws.

(b) Part II - Advance Account Activities This Part includes the Advance Accounts Activities and the limits approved for those activities and indicated in the Second Schedule to the appropriation Act.

(c) Part III – Salary Scales This Part sets out the Salary Scales of the Public Service and is a supporting schedule to the General Estimates.

F.R.7. General Estimates. (1 ) General Estimates of Expenditure are classified in terms of Heads, Programmes, Projects, Objects and Financing Details. Objects are further itemized only where it is considered that separate accounts should be kept for those items of expenditure.

(2) Parliament appropriates provision for expenditure in terms of Heads and Programmes grouped under each Cabinet Ministry.

(3) Recurrent and Capital Expenditure – Government expenditure is categorized into –(a) Recurrent Expenditure and (b) Capital Expenditure. All current expenditures are categorized under Recurrent Expenditure and all expenditures for acquisition, rehabilitation and improvements of assets and development of resources are categorized under Capital Expenditure. This distinction is maintained at every level of budgetary classification and appropriations are made under these two categories.

F.R. 8 Units of Budgetary Classification

(1) Head – A Head of Expenditure is assigned to each Department and Cabinet Ministry. Provision for Public Corporations is made under the Ministry Head. Head is a unit of appropriation and indicates the line of authority and accountability. Classification of expenditure into Heads are based on the Administrative Organization Structure and are clustered under Ministries excepting the Heads of Expenditure of the Departments not grouped under any Ministry. Each Head is given an identification number.

(2) Programme – (i) Programme is a functional unit of appropriation. Programmes should be formulated in order to facilitate listing the functions each department is fulfilling in order to achieve its objectives. (ii) Programme I is reserved for General Administration and is standardized in order to show the distinction between theexpenditure for running the establishment and the expenditure for the services rendered by the establishment.

(3) Project – Projects is a sub division of a programme representing an activity or a group of homogenous activities. It facilitates the costing of each activity and the evaluation of input output data of the activity. Recurrent expenditure projects are numbered consecutively starting from numeral 1 and capital projects are numbered consecutively starting from numeral 101. The first three capital projects are standardized as follows:

101 - Rehabilitation and Improvement of Capital Assets 102 - Acquisition of Equipment 103 - Construction of Buildings

(4) Objects - (i) Object is an economic component of a project. Objects are grouped into broader categories while maintaining Capital Expenditure and Recurrent Expenditure distinction. There are seven categories of recurrent expenditure Objects and seven categories of capital expenditure Objects. The Objects are coded with four digit numbers. The first two digits indicate the economic categories. ( See Appendix I) Coding and legends of Objects are standardized and should not be changed. (ii) The economic categories of recurrent expenditure Objects are :- (1) Personal Emoluments (2) Travelling Expenses (3) Supplies (4) Contractual Services (5) Current Transfers (6) Current Grants (7) Other Recurrent Expenses (iii) The Economic Categories of Capital Expenditure Objects are :- (1) Equipment Outlay, Land Improvements and Structures Outlay (2) Capital Transfers and Subsidies (3) Capital Grants (4) Financial Assets (5) Repayments (6) Rehabilitation and Improvement of Capital Assets (7) Other Capital Expenses The smallest unit of account is the Object Class.

(5) (i) When a standardized Object Class provides for a number of related activities and it is desirable that the nature and cost of each activity should be communicated to Parliament, the object class is divided into consecutively numbered items. Items for which separate accounts are maintained in terms of this regulation will hereinafter be referred to as “ Controlled Items”. The maintenance of separate accounts for expenditure on any other items will depend on the extent of control necessary to be adopted for departmental purposes and need not be shown in the Estimates.

(6) Financing Details of Object Classes - Expenditure under each Object is accounted for under the following accounts and shown in the Estimates by way of following Financing Details. The intention of this classification is to identify the source and ways of funding and to facilitate the systematic accounting of allocation of resources.

Appropriation Law - (Supply Services)

(11) Consolidated Fund General Account (12) Foreign Aid Loans (13) Foreign Aid Grants (14) Reimbursable Foreign Aid Loans (15) Reimbursable Foreign Aid Grants (16) Counterpart Funds

Special Law – (21) Consolidate Fund General Account In all cases source and reference to law or agreement should be indicated.

F.R.9. Order of Presentation of the General Estimates The Estimates of Expenditure are presented by way of narrative Statements and columnar schedules in the following order – (a) Ministry Summary of Expenditure by Departments - Schedule.

(b) Objectives, Main Functions and General Work Programme of the Head of Expenditure – Narrative Statement.

(c) Department Summary of Expenditure by Programme – Schedule.

(d) Programme Expenditure by Project – Narrative statement followed by a Schedule including Financing Summary. (e) Programme Employment Summary – Schedule.

(f) Project Expenditure by Object – Narrative Statement followed by a Schedule with Financing Details.

(g) Details of Objects – Items of work under the Object where necessary only – Schedule. In every Schedule the comparative figures of the two years prior to the budget year are shown.

F.R. 10. Personal Emoluments

(1) Financial provisions for Personal Emoluments, i.e. Salaries and Wages, Overtime and Holiday Pay, Cost of Living Allowance, Uniform Allowances and Other Allowances should be made on the basis of approved cadre. However, provision for Overtime and Holiday Pay should, as far as possible, be made on the basis of actual needs. Each type of allowance should be provided for separately under the appropriate standardized Object Code. (Number and legend) NOTE: Personal Emoluments payable to staff out of Advance Accounts or any source other than General Estimates, should be met from such source.

(2) Grouping of Cadre

(i) Group A Positions This group is composed of policy making top management positions including appointments under the provisions of the Constitution or any other statute, Heads of Departments and Staff Grade appointments to constitutional bodies like Parliament, President, Former President, Ministries or any other post for which Parliamentary authority is considered necessary. Information regarding each post of this group should be shown in the main schedule along with the totals of the group. (ii) Group B - Staff Officer Grade Only the totals of all Staff Grade Officers not included in Group A need be shown under the item on the main schedule of the Estimates. Detailed information should be included in the Detailed Staff Schedule published separately. (iii) Group C - Subordinate Officer Grades Total cadre of and expenditure on all subordinate officer grades as defined in the Establishment Code should be included in this schedule and other details should be included in the Detailed Staff Schedule Published separately. (iv) Group D - Minor Officer Grade Total cadre of and expenditure on officers defined as Minor Grade Officer should be shown in this schedule and other details should be included in the Detailed Staff Schedule published separately.

(3) Staff Schedules All the Staff should be analyzed and shown strictly in accordance with the prescribed format. Detailed Staff Schedule will be published as a separate document to supplement the Programme Employment Summary in the General Estimates.

(4) Combined Services Provision for the sanctioned cadre of posts in the Combined Services in each department should be made in the Estimates of the Department. The sanctioned cadre under each Combined Services also should be shown in the Estimates of the relevant Ministries indicating the Grades, the number of sanctioned posts in each Grade and Salary Scales of such Service.

(5) Posts under Advance Accounts and Other Sources Financial provision for salaries and wages of officers who are employed full time, on Advance Account Activities or are paid from any other source should not be included under Salaries and Wages in the General Estimates but under the relevant Advance Account or other source. A statement of such posts should be submitted to the Director General of National Budget along with the Draft Estimate.

(6) Provision for Vacant or New Posts Provision for vacant or new posts should be made on the basis of the initial salaries of the relevant salary scales, and only for the period from the prospective date of filling of the vacancy to the end of the financial year of estimates.

(7) Seconded Officers When an officer of one department is seconded or loaned to another department or activity, his substantive post will continue to appear under his former Department but no financial provision should be included unless acting arrangements are necessary. The designation of the new post he holds and the Monetary provision therefore should appear under the department to which he is seconded or loaned unless paragraph (6) above applies.

(8) Deployment of Staff An explanatory note should indicate what the present scale of operations of a Programme/Project or Activity is and point out any increases in scales of operation propose to have for the Budget Year and the reasons for scaling up. Always such proposals for increases should be supported with enumeration of increases in benefits or increases in performance in terms of measurable units of work or any other concrete and precise terms. This note should identify the existing resources of man-power, etc., and any possible re-deployment should be indicated. Possible changes of priorities in the current year programmes and projects should be supported by reasons for such change including any policy directions from government.

(9) Surpluses and Vacancies of Staff All staff of the Ministry/Department should be identified in terms of Programmes and Projects. It is necessary that these have to be identified with definite programme and projects, and any surplus staff on low priority projects should be identified and reported to the Department of National Budget for necessary action.

(10) New Staff Proposals (i) Provision for additions to the existing staff should not be included in the draft estimates without prior approval of the Director General of National Budget– FR 71. It is essential that this approval should be sought well in advance to enable the Director General of National Budget to have the necessary investigations made on the need for additional staff. Every such application should indicate whether the posts are sought in respect of current activities or for new activities, under the Programmes and Projects. Full particulars should be provided on the prescribed form – specimen at appendix 1.2 requests for staff not tied up with specific Programmes and Projects would not be considered at all. No post shall be created with retrospective effect extending back to a date in a lapsed Financial Year. (ii) If additional staff is sought for new activities, they should be explained in detail. The Estimate proposals should not be purely a recital of requirements. Programme project format provides an occasion for evaluation of on-going programmes and projects, of balancing one project against another and of identifying in precise or measurable terms, the benefits of further investment. It is possible that the Secretary/Head of Department would be in a position to meet his needs by revising the priorities amongst existing projects so that if he is scaling up the activities under one project, he could achieve this with the existing resources and allocations by scaling down on other projects of low priority. (iii) Any new staff proposals should indicate how the present staff are deployed and what percentage of their time is being spent on the various activities of the project. This information also should be furnished along with the new staff proposals so that it would be possible to examine at the Department of National Budget whether the existing staff can cope with any increases in the scale of activity. It should be the endeavor of the Head of Department and Secretary to examine that full use is being made of the existing manpower and other resources under a project before requests for new staff are made on the grounds of increased level of activity. It should be noted that additions or variations, either in cadre or in monetary provision should not therefore be haphazardly proposed but be made in specific relation to definite programmes with measurable output. Alternatives of more effective and perhaps economical methods of attaining the same objectives should be considered. Details of such examination should be reported to the Secretary for direction with regard to choice of alternatives. Possibility of mobilizing resources from one programme or a project of lesser priority to another of high priority should be examined and reported to the Director General of National Budget. There should be a clear understanding of the impact of any increase in one type of resource on other resources available to a programme or project, e.g. an increase in the cadre of Inspectors which necessarily involves an increase in expenditure on traveling, etc. (iv) Capital projects within a programme provide additional capacity to the programme and increase of such capacity by itself may require additional recurrent expenditure on manpower, materials and other resources. Any additional resources sought by way of increase in cadre and monetary provision should be identified separately and justified with reference to additional activities, and increase envisaged on output, benefit, etc.

F.R. 11. Estimation of Other Recurrent Expenditure (1) Travelling Expenses – Circumstances under which increases are sought if any, on this object group, should be fully explained. Ordinarily no increase will be allowed except when new staff is approved or new activities are allowed for the budget year. Computation of costs should be shown in detail by an annexure to the Statement so that examination is possible as to the causes of increases.

(2) Supplies - Invariably this group of objects of expenditure becomes significant next to the staff costs and a great deal of attention should be paid to the computation of this. As pointed out earlier economies have to be exercised and with this end in view wasteful methods have to be eliminated. For purposes of analysis, detailed break-down of provision sought under this Object group should be shown and if increases are sought, these should be identified with increased levels of activity and increases in output.

(3) Contractual Services – Here too economies have to be exercised very carefully. A detailed breakdown of the Objects of expenditure coming under this group should be given as an annexure to Form B. If increases are sought, reasons for such increases should be explained fully.

(04) Current Transfers, Current Grants, Other Recurrent Expenses - Statement showing the detailed analysis of the provisions sought under each object of these groups, should be forwarded. Computation of the provisions should be based on policy directives and statutory obligations. These statements should be supported by reference to such approvals and requirements. For instance, in case of Grants to provincial Councils approval of the Finance Commission should be forwarded.

F.R.12. Estimation of Capital Expenditure (1) Rehabilitation and Improvement of Capital Assets - Nature of rehabilitation or improvement and the need for rehabilitation or improvement should be fully explained. Where vehicles and equipment are involved their age composition should be furnished. The estimated cost of each object under this group should be stated.

(2) Equipment outlay, Land, land Improvement and structures outlay - If an increase is sought on this object of expenditure, the need for the increase should be explained eg. Questions like whether is it by way of increase in number of men and therefore increase in furniture requirements or is there an increase in the level of activities using various equipment or is it for replacement should be covered by explanatory notes. If the equipment is for a specific project it should be stated whether provided for under the project, whether the requirement of the particular projects cannot be met out of the available Machinery, Equipments, Vehicles, Buildings, Structures, etc., and what is proposed to do with such capital assets when the project is over.

(3) Constructions and other Development Projects - Particulars regarding Projects which have been already commenced and continued in the budget year and having a Total Cost Estimate should be forwarded to the Department of National Budget with explanatory notes for inclusion in the Annual Estimates. Particulars regarding new projects which have been duly approved should also be forwarded with explanatory notes along with references to Project documents like Project Reports, Funding Agreements, Implementation Programmes, etc. (see F.R.3.)

(4) Acquisition of lands and buildings - Block Provision is made for all acquisitions of lands and buildings for Government Departments under Estimates of the Ministry in charge of the subject of Lands. Normally provision is not made under other Government Ministries and Departments to purchase land and buildings.

F.R.13. Miscellaneous Services. Financial provision for services of a special character , which cannot appropriately be provided for as direct expenses under a particular department, is made under Head “Miscellaneous Services” controlled and operated by the Treasury, Director General of National Budget.

F.R.14. Token Provision. No Token Provision should be included in the Annual Estimates except under very special circumstances with Specific approval of the Director General of National Budget.

F.R.15. Advance Accounts Activities

(1) Categories; The Estimates relating to Advance Accounts show four types of limits, viz., (a) Maximum limit of Expenditure.

(b) Minimum limit of Receipts credited to the Accounts.

(c) Maximum limit of Debit Balances.

(d) Maximum limit of Liabilities.

(2) Capital Expenditure of Advance Account activities is not included in these limits. Such expenditure is provided under the appropriate Programmes/Projects in the General Estimates. The replacement of a depreciated assets will however, be met from the Depreciation Reserve Fund. The replacement cost will, in addition, be shown under the Capital Project, in the Estimates, but no monetary provision will appear. Such replacement cost should be shown by way of a footnote indicating that the expenditure will be met from Reserves.

(3) Adequate explanatory notes should be furnished on the scale of operations on direct use of labour, materials and direct expenses and also on administration and other expenses. Need for increase in scale of activity should be explained fully with reference to any policy directives of Government. Targets of performances should be indicated. If a certain strength of staff is being made use of, whether this could be reduced or if the staff is to be increased whether any increased performances is planned should be indicated. All questions vide the prescribed forms should be adequately answered so that a rational analysis on the need for revision of limits if any, could be made.

(4) Each Advance Account Activity would fall into one of the following types and grouped under Heads of Expenditure. Coding for identification purposes is done with five digit numerals, the first three digits being the head Number e.g. Advance Accounts under Head No. 481 48101, 48102, 48103, etc.

(5) Types of Advance Account

(i) Production Advance Accounts (ii) Development Advance Accounts (iii) Trading Advance Accounts (iv) Stores Advance Accounts (v) Advances to Public Corporations (vi) Advances to Public Officers (vii) Miscellaneous Advance Accounts

(6) Provision for expected losses If a net loss expected in the working of an Advance Account Activity during the financial year, and incurring of such loss is approved by the relevant authority, provision for the estimated net loss should be included in the Annual Estimates under an Item in the appropriate standardized Object Code.

(7) Losses in previous financial year The procedure to be followed in these cases is given in Chapter viii, Advance Accounts. F.R. 513

F.R.16. Other Levels of Government. (1) Any provision for Other Levels of Government should be provided in the National budget by way of grants, or contributions. In the case of provision for Provincial Councils, the prescribed format should be followed. Monetary provisions in the National Budget for Provincial Councils is made under the Line Ministry in charge of the Provincial councils and the Secretary of that Ministry is responsible for the formulation of budgetary proposals in consultation with respective Chief Secretaries and the Finance Commission.

(2) Draft Estimate Proposals for all projects which are included in the Public Investment Programme of the Government in relation to devolved functions which have to be implemented by Provincial Councils will have to be included under the Heads of Expenditure of the relevant Ministry or Department. These proposals should be prepared in consultation with the respective Provincial Councils. Instructions on the preparation of these estimates should be sent by the relevant Secretary to the respective Chief Secretaries.

(3) No financial provision should be included in the Estimates of the Ministries or Departments for the staff released or earmarked for release to Provincial Councils. The requirements for such staff will be provided for under the block grants for the Provincial Councils. The category and the numbers of the staff involved in provincial administration should, however be distinctly identified and shown in the appropriate programme staff schedule.

F.R. 17. State Corporations . (1) Secretaries, when seeking budgetary support for Capital Projects implemented by State Corporations, Boards and other Corporate Bodies, should indicate the quantum of funds required and how the balance sum, if any, will be found and whether any further sums will be required in subsequent years. Budgetary support will appear as a separate capital project under the votes of the particular Ministry.

(2) Even if budgetary support is not sought, plans of project within the approved Corporate Plan, should be sent to the Director- General, National Planning for approval with a copy to Director General of Public Enterprises.

(3) Total Cost Estimates should be duly sanctioned and shown in the estimates irrespective of whether the project is wholly or partly financed by the Government budget.

(4) Public Enterprises should revise their charges and prices in order to yield an operational surplus, so that their current expenses are met out of the funds generated. Losses and shortfalls will be accepted for support only where there is a specific government decision to subsidise the operation of the public enterprise concerned.

(5) Non-profit Oriented Public Corporations and the Public Institutions wholly financed by government should not seek enhancement of their activities unless prior approval of the government is obtained for those specific activities. Increases in budgetary support would not be considered unless such specific approval is available.

F.R.18. Grants & Subsidies. (1) Financial provision for grants to non public sector bodies over which parliament has no control is voted by Parliament for certain specific purposes and subject to prescribed conditions. Provision for such grants as appearing in the Estimates cannot be altered without Parliamentary authority.

(2) Financial provision for subsidies will be in respect of payments to be made by Government to meet the difference between the actual cost of a supply or service and the price at which the Government has directed that such supply or service should be sold or rendered.

F.R.19. Special Law Services. (1) As expenditure on Special Law Services is a charge on the Consolidated Fund, already imposed by law, it is not included in the Appropriation Act.

Examples of such services are -

(a) Salary Allowances and pension of the President – Article 36 of the Constitution.

(b) Salaries of Staff and Government share of Contributions, etc., of the Public Service Provident Fund – (P.S.P.F.)

(c) Repayment of medium and long term foreign loans ( Foreign Loans Act 29 of 1987)

(2) However, provision for such expenditure is shown in the Annual Estimates and particulars of the Law under which the expenditure is authorized, are also distinctively indicated against the legend of the relevant budgetary unit. Such expenditure should be included in the Programme/Project Structure.

(3) In providing for Special Law Expenditure, any terms and conditions of the Law under which the expenditure is met, are taken into consideration, e.g., the Law may prescribe a limit on a grant. In this case, if the grant is paid in annual installments, provision should not be made after the full grant has been paid.

F.R. 20. Total Cost Estimates

(1) The Total Cost Estimate ( if revised, the revised Total Cost Estimate) of any capital work should be shown in a special column in the Annual Estimates. In addition, information should also be provided in separate columns as follows:-

(a) Anticipated date of completion of work. (a) Actual expenditure up to the end of the year prior to the year in which the draft estimates are being prepared.

(b) The Actual expenditure in the year prior to the year in which the draft Estimates are being prepared. (d) Estimate for the year in which the draft Estimates are being prepared. (e) Estimate for the budget year. The total (b) plus (d) plus (e) should not exceed the approved Total Cost Estimate.

(2) The Total Cost Estimate of each project should be determined on the basis of a carefully priced Bill of quantities which is supported by detailed schedules showing requirements of material, labour, plant, and equipment utilization and schedules of prices on which the Bill of Quantity rates were arrived at. There should be supporting documents to monitor price changes and translate them to rate changes, as a matter of routine, for use if needed. The Total Cost Estimate prepared for Examination of Works Proposals in terms of Financial Regulations should be prepared on this basis adding 10 percent for Contingencies and a further 10 percent to allow for escalation of prices within that year. If the work has to be phased over more than one year, the allowance for price escalation should be 10 percent for the first year, 20 percent for the second year, 30 percent for the third year and so on, in respect of the work to be done in each year. The allowance for Contingencies and price escalation should be indicated separately in the preparation of Total Cost Estimates and should not be disclosed even at the time of calling for tenders or at negotiation with the Contractors, when the exact approved Total Cost Estimated (excluding these percentages) should be used.

(3) Authority for approving a Total Cost Estimate will be either the Cabinet or Department of National Planning or the Department of National Budget as the case may be ( see F.R. 35 & F.R. 36).

F.R. 21. Block Provision. (a) When a Capital Budgetary project, already approved in terms of F.RR 35 and 36 and provided for in the Estimates, comprises a number of similar but separate Projects or Components, and these cannot be separately itemized in the Estimates, the Total Cost Estimates, and the particulars in the other column referred to in F.R. 20(1), may be shown in the form of “ Block Provision” for all the contemplated items.

(b) Projects or items of works each costing not more that Rs. 5,000,000 may be incorporated in a “Block Provision” if separate items cannot be detailed at the time provisions is sought in the Estimates. Projects or items of works each estimated to cost over Rs. 5,000,00 should be separately itemized and shown in the Estimates.

( No F.RR. Issued Under Nos. 22 – 33)

Section 3 — New Proposals

Section 3 - New Proposals

F.R. 34. New Project Proposals - Capital Expenditure. (1) New Projects will be admitted in the Budget according to the availability of resources and on the basis of investment priorities approved by Government. It should be noted that only projects which have been approved in accordance with the prescribed approval procedures and included in the Public Investment Programme will be accepted for financing. It should also be noted that a new phase or the extension of an ongoing project in the Total Cost Estimate of which the activities to be undertaken under the new phase or the extension are not included, should be treated as a new project and the prescribed approval procedures should be followed.

(2) Before inclusion of new Projects in the Draft Estimates of Expenditure the Director General of National Budget should be satisfied that following steps regarding the new projects have been taken in addition to approvals referred to in F.RR 35 & 36.

(a) The firm Total Cost Estimate of the Project should be compiled.

(b) If it is a foreign aided project negotiations should be completed and agreements signed or confirmed.

(c) Programming of implementation of the project and phasing of expenditure over the period required to complete the project should be finalized.

(d) Arrangements should be made to monitor and co-ordinate the activities necessary for the completion of the project and to provide for the operation and maintenance of the project after completion.

F.R. 35 (1) Preliminary approval ( Approval in Principle). – Projects and project ideas generally originate within and be sponsored by a particular Ministry or Department which is also responsible for projects originating form Statutory Bodies or Public Enterprises within its ministerial responsibilities. Once the project has been identified and some initial preparations completed it will be submitted for preliminary approval. All projects which are being submitted for preliminary approval must be submitted on the approved Preliminary Approval Form.

(2) Preliminary approval is required before any of the following activities can take place.

(a) Inclusion of a project in the Public Investment Programme.

(b) Incurring of expenditure on design, preparation or engaging consultants to undertake feasibility studies ( including studies funded by foreign donors)

(c) Authorization by the External Resources Department the negotiations between a line Ministry and a potential aid donor, or assisting in locating a prospective donor.

(d) Listing of Projects in the Compendium of ‘New Projects’ which is produced periodically for aid donors.

(e) Obtaining budget funds and commencing implementation of small projects.

(f) Commencement of the implementation of any sectoral plan or programme.

(3) Approved sectoral plans and programmes will be formally recorded in the Public Investment Programme, together with brief summaries, costs, expected projects etc. subject to the final approval later. In the case of Sectoral Plans and Programmes the completed Preliminary Approval Form must accompany the full plan/programme for which approval is being sought. The form should also be completed for small projects whether or not they form part of a wider sectoral plan. (4) The National Planning Department will undertake an appraisal of all projects submitted for Preliminary Approval. In the case of small projects which form part of an approved Sectoral Plan or Programme approval may be granted by the National Planning Department. In all other cases the project or plan will be submitted along with the comments of the National Planning Department to the Committee of Development Secretaries. The National Planning Department may consult the Director General of National Budget over potential implications on the Budget. Environmental problems may be referred to Central Environment Authority.

(5) The Committee of Development Secretaries will consider all proposals for Preliminary Approval excepting small Projects which are parts of approved Sectoral Plans or Programmes. It will consider comments from the National Planning Department and from other relevant Ministries and Departments.

F.R. 36. Final Approval. (1) Sectoral Plans or Programmes and Large Projects should receive Final Approval. Final Approval for all large Projects is necessary before –

(a) the Project can be listed as “ accepted” in the Public Investment Programme.

(b) it can appear in the Government Budget and have funds made available for implementation whether from domestic or foreign sources.

(c) final negotiations between the Director of External Resources with prospective donors for the conclusion of an aid agreement can take place.

(2) Large Projects are of two types namely -

(a) Commercial Projects - Commercial Projects are projects which will produce output of goods or services which will be sold at market prices. These will include any projects for manufacturing industrial goods or growing agricultural produce. Most of such projects are executed either through Advance Account Activities (see F.R. 15) or by Public Corporations.

(b) Non-Commercial Projects - Non-Commercial Projects will generally include those projects which provide services to the public for which market prices are not charged. Such projects are found within the General framework of economic or Social Infrastructure or overheads. Certain projects in industry or agriculture, for example, research or extension projects would also fall into this category.

(3) When submitting large projects for final approval information should be supplied in the formats prescribed by the National Planning Department.

(4) On receipt of a request for the final approval the National Planning Department will prepare a report on the project and submit it to the committee of Development Secretaries.

(5) Once the project has received approval from the committee of Development Secretaries it will be forwarded to the Cabinet for further consideration. If considered feasible it will receive Final Approval and would be included in the Public Investment Programme.

(No F.R. Issued Under 37)

F.R. 38. Specific Treasury Authority is also required before the following are incorporated in the Draft Estimates:-

(i) New Heads, Programmes and Projects: For new services which would not properly fall within the ambit of existing Heads, Programmes and Projects.

(2) Changes of designation and alternations to cadre, salary scales, etc. Changes referred to in F.R. 71(1), should not be introduced into the Draft Estimates, unless approval in terms of that Regulation has been already granted.

F.R. 39. New Advance Accounts in the Draft Estimates. When it is proposed to create a new Advance Account in the Draft Estimates of a Department, prior authority of Director General of Public Enterprises should be obtained for the purpose. An application for such authority should be forwarded through the Chief Accounting Officer before the 15th of July each year or before such other date as would be indicated by the Treasury. The following particulars should be furnished.

(a) Full details of the activity proposed to be carried out.

(b) The Capital Expenditure involved. This will not be a charge to the Advance Account. (see F.R. 500(4)).

(c) All the administration and other expenses which are chargeable to General Estimates of Expenditure.

(d) The administration and other expenses which are chargeable to the Advance Account, along with full details of cadre, scales of salary, etc.

(e) The anticipated receipts of the activity. ( Classified details should be provided).

(f) If a loss is anticipated, the reasons therefore, and why the activity should be created and carried out despite an anticipated loss.

(g) The proposed limits as indicated in F.R. 15.

(h) A budgeted Trading Account, and a Profit and Loss Account or Revenue and Expenditure Account, as the case may be.

F.R. 40. Revision of Total Cost Estimate. The Total Cost Estimate of any work, supply or service already appearing in the current year’s Estimates, cannot be increased without prior authority under Financial Regulation 72.

F.R. 41 – Equipment (1) Office Equipment – Departments which intend to procure new accounting and other specialized office equipment such as Computers, Photo Copiers etc., or to replace such unserviceable machines, should obtain prior approval of Secretary before purchasing them the Secretary should satisfy himself of the necessity before granting the approval.

(2) Other equipment such as refrigerators, Air Conditioners, Motor Vehicles, Drawing Room Suites, office requisites such as Video apparatus or any equipment of a special nature where the cost of an items is Rs. 20,000 or more should receive prior approval of the Secretary for purchasing them.

(No F.RR. Issued Under Nos. 42-49)

Section 4 — Preparation, Submission and Passing of Estimates of Expenditure

Section 4 – Preparation, Submission and Passing of Estimates of Expenditure

F.R. 50. Responsibility for preparing annual Estimates of Expenditure. It is the responsibility of the Accounting Officer to see that the Draft Estimates relating to his department are prepared in conformity with these Regulations. He is responsible particularly to ensure:-

(i) that all services which can be reasonably foreseen are included in the Estimates and that they are within the capacity of his department during the financial year; (ii) that the Estimates have been prepared as completely and accurately as possible; (iii) that the Estimates have been framed with due regard to economy and efficiency; (iv) that there is no delay in complying with the procedure arising out of preliminaries to the Estimates;

(v) that the requisite authority has been obtained, where necessary, before provision is made in the Estimates; and (vi) that Estimates are sent in due time and in proper form.

(No F.RR. Issued under Nos. 51 and 52)

F.R.53. Acquisition of land and buildings. (1) Acquisition of land and buildings should be provided only for approved Programmes and Projects, Land should be acquired only if suitable state land is not available for the purpose. If state lands is available in the vicinity private land should not be acquired unless the available state land has proved to be absolutely unsuitable for the purpose and also the acquisition of developed land should be avoided as far as possible. Buildings should be acquired only where they can be conveniently and economically converted to departmental use or where the acquisition is unavoidable.

(2) When acquisition is necessary Head of department should obtain a valuation report from the Chief Valuer for both Land and Buildings.

(3) Before 1st of February of every year, each Account Officer should submit to his Chief Accounting Officer, a schedule of all the proposed acquisitions of his department, in respect of the next financial year, along with the valuation reports and the following information:- Land - (a) Name of land, (b) Approximate extent, (c) Purpose of acquisition, (d) Cost,

Buildings -(a) Plans of any buildings on the land, (b) Nature and cost of any repairs, additions and improvements, including water, lighting, drainage and power,

(c) Whether there is any possibility of the buildings lying idle owing to delay in providing equipment or staff.

(4) The Chief Accounting Officer will forward a schedule of all the proposals approved by him relating to the departments of his Ministry in order of priority to the Director General of National Budget before 15th February of each year. The Treasury will indicate to the Chief Accounting Officer the items approved before 1st March. Each Ministry will thereafter forward a schedule of the items approved by the Director General of National Budget, to the Ministry in charge of the subject of Lands before 15th March indicating the approval of the Director General of National Budget has been obtained.

(5) Provision in a block sum for acquisition of items approved by the Director General of National Budget will thereafter be made by the Secretary to the Ministry in charge of the subject of Lands.

(No F.R. Issued Under No.54)

F.R. 55. Forms for rendering information for the Draft Estimates should be prepared on the prescribed format and extracts of the current year’s Estimates suitably amended. The current year’s Estimates should normally form the base of the Draft Estimates, and the provision for the ensuing year should be inserted in a column adjacent to that current year. The following forms are prescribed for rendering of information required for the preparation of the Annual Estimates. ( See Appendix 1.1) (1) Memoranda Form A - Approved Cadre and Personal Emoluments this form is designed to supply information regarding cadre employed. It should contain all the information regarding the staff to be employed during the budget year. Statements on Form A need not be sent, along with the Draft Estimates proposals but should be available for reference if required by the Department of National Budget at a later stage in the course of preparation of the Annual Estimates.

(2) Memoranda Form B - Recurrent Expenditure This form is designed to supply particulars of all items of Recurrent Expenditure including Personal Emoluments and should indicate – (a) Summary of Expenditure of the Department (b) Programmes Summary by Project (c) Project Expenditure by Object Code Completed statements on Form B should be rendered along with the Draft Estimates proposals.

(3) Memoranda Form C - Capital Expenditure (Excluding Expenditure on New Works) This form is used for supply of information of expenditure on Capital projects commenced in previous years or current year and would continue during the ensuing budget year. Completed Statements on form C should be rendered to the authorities indicated in the Budget Calendar on the due dates.

(4) Memoranda Form D – Capital Expenditure (New Works Proposals) This form is designed to supply of information regarding provision for expenditure on capital projects to be commenced during the ensuing budget year. Completed statements on Form D should be rendered to the authorities as indicated in the Budget Calendar.

(5) Memoranda Form E – Source of Financing This form is designed to supply the information regarding source of funding required to be provided in the Annual Estimates of Expenditure. Particular care should be taken to include all the information required. Completed Statements on Form E should be sent as prescribed in the Budget Calendar.

(6) Memoranda Form F - Work Accomplishment This form is used to supply information regarding work accomplishment for the budget year. One form should be used to indicate each “unit” of work measurement under a project. Completed Statements on Form F should be rendered as indicated in the Budget Calendar.

(7) Memoranda Form G - Advance Accounts Information on this form is required for revision of the limits in respect of existing Advance Accounts and also for the establishment of new Advance Accounts. Completed Statements on Form G should be rendered as prescribed in the Budget Calendar.

Notes –

  1. Expenditure of the past financial year. The published accounts of the Government, and the Appropriation ( Votes) Ledgers, reconciled as far as possible with the Treasury records, are the sources from which the figures of actual expenditure of the past financial years should be obtained.

  2. New Posts. ( i.e. those not hitherto shown in the Estimates) should be inserted in red ink in the extracts, so that attention may be drawn to them.

  3. Contingencies. No provision should be made for expenditure which is not likely to be incurred in the year of Estimates.

F.R. 56 . Submission of Estimates (1) By Accounting Officer – The Draft Estimates proper made up of the extracts and the relevant forms together with the explanatory notes should be forwarded in triplicate to the Chief Accounting Officer to reach him not later than 1st April, or any earlier date as may be prescribed by him. The Estimates of Departments, not grouped under any Ministry, should be sent in duplicate direct to the Director General of National Budget before 1st May.

(2) By Chief Accounting Officer – The Chief Accounting Officer will examine the Estimates to ensure that they are in order, and that the requirements of F.R. 50 have been complied with. He will thereafter forward to the Director General of National Budget in duplicate the Estimates of all departments of his Ministry, before 1st of May.

F.R. 57. Treasury Decisions on Draft Estimates. The Treasury after considering the Draft Estimates in consultation with the respective Secretaries and Heads of Departments, where necessary, will forward its decisions to the respective Secretaries and Heads of Departments. The Treasury will, thereafter, incorporate its decisions in the Draft Estimates. Once the Draft Estimates are thus finalized, the treasury will not entertain any requests for further amendments as the overall budgetary position would by then have already been determined any request for additional funds would necessitate a reassessment of the position. The finalized draft Estimates of Expenditure are then presented to Cabinet for approval.

F.R. 58 . (1) Submission of Estimates to Parliament. - Treasury, after obtaining Cabinet approval for the finalized Draft Estimates will send the approved Estimates to the Government Printer for printing. The printed Draft Estimates will be treated as a confidential document until presented to Parliament by the Minister in charge of the subject of Finance. The Draft Estimates of Expenditure will, thereafter, to the extent to which such expenditure has not been previously authorized by law, be embodied in the Appropriation Bill. This Bill will be submitted by the Minister in charge of the subject of Finance to Parliament, along with the printed Draft Estimates.

(2) Appropriation Bill - The Appropriation Bill provides for the services of the financial year, to authorize the raising of loans in or outside Sri Lanka, for the purpose of such service, to make financial provision in respect of certain activities of the Government during that Financial Year, to enable the payment, by way of advances out of the Consolidated Fund or any other fund or moneys of, or at the disposal of, the Government, of moneys required during that financial year for expenditure on such activities, to provide for the refund of such moneys to the Consolidated Fund, and to make provision for matters connected with, or incidental to, the aforesaid matters.

(3) Committee Stage Amendments – The printed Draft Estimates is intended to be the final form of the Draft Estimates presented to Parliament. However, every urgent and essential proposals, or changes to the printed Draft Estimates, the necessity for which has arisen since the preparation of the Appropriation Bill, may at this stage be submitted to the Cabinet, on a personal direction of the Minister concerned, through the Minister of Finance. It the Cabinet approves the proposals or changes they will be submitted for consideration by Parliament in Committee along with the printed Draft Estimates and the Appropriation Bill. Such proposals are referred to as “Committee Stage Amendments.”

(4) The Appropriation Act - The Committee Stage Amendments as approved by Parliament in Committee are incorporated in the Estimates. The Appropriation Bill incorporating the consequential amendments, is passed by Parliament and becomes law when the certificate of the Speaker is endorsed thereon in terms of Article 80(1) of the Constitution. It is, thereafter, referred to as the “Appropriation Act”. The Appropriation Act does not in itself provide complete authority for expenditure. ( see F.R. 90)

(No F.RR. Issued Under Nos. 59 – 64).

Section 5 — Variations to Estimates of Expenditure

Section 5 – Variations to Estimates of Expenditure

F.R. 65. (1) The Annual Estimates of Expenditure approved by Parliament along with the Appropriation Act and Estimates of Expenditure approved by resolution passed in Parliament must be regarded as prescribing within hard and fast limits the purposes and the sums for which the provision prescribed may be spent, the cadre which maybe employed, and the total cost of particular projects. The specific purposes and the sums provided under the Heads, Programmes, Projects, Objects, Items and Financing details should not be varied without appropriate authority.

(2) Authority exists, under certain circumstances -

(i) to transfer any sum that has been allocated by appropriation Act to recurrent expenditure of any Programme appearing under any Head specified in the Annual Estimates of Expenditure, but has not been expended or is not likely to be expended, to Capital Component of another Programme under the same Head of Expenditure. (ii) to transfer savings from Projects standardized Object Classes, Items or Financing Details to other Projects, standardized Objects Classes, Items of Financing details of the same Programme (see F.R. 66) (iii)to create a new Project a standard Object class, an Item or a Financing detail ( see F.R. 68). (iv) to withdraw in whole, or in part, any amount previously released for expenditure (in accordance with the provisions of the Appropriation Act).

(v) to approve variations in the Cadre of an establishment and the alteration of Salary Scales etc, ( F.R. 71). (vi) to approve variations in the Total Cost Estimate of a Project or work (see F.R. 72). (vii) to approve increases in Heads of Expenditure – ( see F.R. 74) (viii) to vary the prescribed limits of Advance Accounts - ( see F.R. 73) (3) Virement Procedure: - Transfer of savings in the manner referred to in FR 65(2) (i), (ii) & (iii) above and FR 69 is generally referred to as “ Virement” Procedure.

(4) When Virement is not appropriate. - Virement Procedure cannot, and should not be adopted -

(j) to transfer savings in a Head of Expenditure to another Head of Expenditure. (ii) to transfer savings in a provision for Capital Expenditure to Recurrent Expenditure of the same Programme or to Recurrent or Capital Expenditure of another Programme under the same Head. (iii) to transfer savings from a Special Law provision to a Appropriation Law provision ( Supply Service), between Special Law Service provisions or from Appropriation Law provision to a Special Law provision. (iv)to create a project, Standard Object, Item or Financing detail for a new Special Law Service unless authorized by Law passed in Parliament.

(v) to transfer savings in a provision if it involves:-

(a) transfer of Savings from any Foreign Aid Financing Detail to Consolidated Fund Financing Detail.

(b) transfer to savings from a direct Foreign Aid Financing Detail to a Reimbursable Foreign Aid Financing Detail or to a counterpart Funds Financing Detail.

(c) Transfer of savings from a Counterpart Fund Financing Detail to a Consolidated Fund Financing Detail. (vi) to create or increase or transfer savings from provision for grants or subsidies to any specific institution, agency or individual (F.R. 18) (vii) to transfer savings from provision made for covering up of losses in the Working of Advance Account Activities. (viii) If the additional or new expenditure envisaged is not approved by the appropriate authority and involves a drastic change in the scale of operations from that presented in the approved Estimates; or if the proposed new service is one which there is reason to believe, Parliament would wish to consider in advance; or if such service will commit the Government to expenditure of large sums of money in the future years. (ix) Unless the savings indicated are definitely available; or anticipated beyond reasonable doubt.

(x) If the savings arise through postponement of a project appearing in the Estimates approved by Parliament and can be implemented in the course of the Financial year. (xi) to transfer savings from provision made under a Supplementary Estimate or other Resolution. (xii) in violation of any other restriction imposed by footnotes in the printed Estimates. (xiii) in violation of any other specific restriction imposed by Treasury circulars or otherwise. (xiv) If the transfer is from or between the Object Codes in the Rehabilitation and Improvements of Capital Assets Object Category.

(5) Changed of Legend:

(a) Change in the legend or title of a Programme would not be allowed during a Financial year.

(b) Change in the legend or title of a Project would not be allowed if it is not approved by the proper authority or if it involves radical change in the objectives or policy relating to the project. Only changes necessary for technical reasons or correction of errors would be approved. All Amendments of Legends should be specifically approved by the Secretary to the Treasury, Deputy Secretary to the Treasury or by an officer authorized by the Secretary to the Treasury.

(c) Changes in the legends of the standardized “Object Classes” of expenditure would not be permitted.

(d) The amendments in a Financing Detail of a Project would not be permitted unless there are technical reasons to do so or there is an error. All such amendments should be authorized by the Secretary to the Treasury, Deputy Secretary to the Treasury or by an officer authorized by Secretary to the Treasury.

F.R. 66 Transfer of Financial Provision – Virement Procedure

(1) When the financial provision appropriated in the Estimates to any Programme, Project, Object Class, or Item of a Head of Expenditure is found to be inadequate for expenditure during the financial year and is likely to exceeded, and if the relevant Account Officer and Chief Account Officer are satisfied with regard to the necessity for additional financial provision, savings, which are likely to be available during the financial year, under any other Programme, Project, Object Class, or Item of the same Head of Expenditure may, subject to FR 65, be transferred to cover such anticipated excess expenditure in the manner specified below. No such excess expenditure should be incurred until such transfer is authorized by the appropriate authority.

(2) Transfer between Programmes:

(a) Capital Expenditure : It should be clearly understood that provision cannot be transferred out of the capital expenditure component of any Programme under which it is provided.

(b) Recurrent Expenditure : Transfer of savings from a recurrent expenditure provision of any Programme under any Head of Expenditure to the capital expenditure provision of the same Programme or to the recurrent expenditure provision or capital expenditure provision of any other Programme under the same Head of expenditure should be ordered by the Secretary to the Treasury or any other officer authorized by him as provided for in the Appropriation Act. Transfers between Programmes can be done only if the Appropriation Act provides for such transfers.

(c) Applications : Applications for transfer in respect of this sub- section should be forwarded to reach the Director General of National Budget in sextuplicate on form General 271 before the 31st December of the financial year.

(3) Transfer between Projects of a Programme:

(a) Capital Expenditure: Transfer of financial provision between capital expenditure Projects of a Programme should be authorized by the Secretary to the Treasury/Deputy Secretary to the Treasury or any other officer authorized by Secretary to the Treasury.

(b) Recurrent Expenditure : Transfer of financial provision between recurrent expenditure Projects of a Programme should be authorized by the Secretary to the Treasury /Deputy Secretary to the Treasury or any other officer authorized by Secretary to the Treasury.

(c) Applications : Applications for transfers in respect of (a) and (b) above should be forwarded to reach Director General of National Budget in sextuplicate on form General 233 before the 31st December of the financial year.

(4) Transfer between Object Classes of a Project :

(a) Capital Expenditure : Transfer of financial provision between Object Classes of a Capital expenditure Projects should be authorized by the Secretary to the Treasury/Deputy Secretary to the Treasury or any other officer authorized by Secretary to the Treasury.

(b) Recurrent Expenditure : Transfer of financial provision between Object Classes of a recurrent expenditure Projects should be authorized by the Secretary to the Ministry concerned/ Chief Accounting Officer.

(c) Applications : Applications for transfers in respect of (a) and (b) above should be forwarded to respective authorities in sextuplicate on Form General 233 on or before the 31st December of the financial year.

(5) Transfer between controlled Items of a Project :

(a) Capital Expenditure : Transfer of financial provision between controlled/ Items of expenditure projects should be authorized by the Secretary to the Treasury/Deputy Secretary to the Treasury or any other officer authorized by the Secretary to the Treasury,

(b) Recurrent Expenditure: Transfer of financial provision between controlled/Items of a recurrent expenditure projects should be authorized by the Head of Department/ Accounting Officer.

(c) Applications : Applications for transfers in respect of (a) and (b) above should be forwarded to respective authorities in sextuplicate on Form General 233 on or before the 31st December of the financial year.

(6) Figures of Expenditure to be furnished in application: In every application for transfer the financial provision allocated in the Estimates, the actual expenditure to the latest date for which figures are available, the anticipated expenditure for the rest of the financial year and the additional financial provision required or anticipated savings under each Object Detail/Item involved in the transfer should be clearly indicated.

(7) Adjustment of provision to be noted in the Appropriation (Votes) Ledgers: In order to ensure that the authorized financial provision under the Programme, Project, Object Class, or Item is not exceeded the transfer of provision should be noted in the Appropriation (Votes) Ledgers after the necessary authority for such transfer has been granted.

(No F.R. Issued Under No.67)

F.R.68. Creation of New Projects, Objects Classes, Object Details and Items. If any contemplated expenditure is within the ambit of a Programme but not appropriate to any of its existing Project/Object Classes/Items and if there are sufficient savings definitely available under one or more of such Project/Object Classes/Items or such Programme or any other Programme, the creation of new Projects/ Object Classes/Items and the transfer thereto such savings may, subject to Financial Regulations 65 and 66, be authorized in the manner specified below:-

(i) Creation of new Projects : Creation of new Projects, whether recurrent or capital, should be authorized by the Secretary to the Treasury/Deputy Secretary to the Treasury or any other officer authorized by the Secretary to the Treasury. (ii) Creation of new Object Classes ; Creation of an Object of expenditure outside the standardized list is not permissible. Creation of a new Object Class under a Project should be authorized by the Secretary to theTreasury / Deputy Secretary to the Treasury or any other officer authorized by the Secretary to the Treasury.

(iii)Creation of new Items :

(a) Capital Expenditure : Creation of a new Item of Expenditure under a Capital Expenditure Project should be authorized by the Secretary to the Treasury/Deputy Secretary to the Treasury or any other officer authorized by the Secretary to the Treasury.

(b) Recurrent Expenditure: Creation of a new Item under a Recurrent Expenditure Project should be authorized by the Secretary to the Ministry concerned/ Chief Accounting Officer. (iv) Applications : Applications in respect of (i), (ii) and (iii) above should be forwarded to the respective authorities in sextuplicate on Forms General 271 or 233 as prescribed in F.R. 66 on or before the 31st December of the financial year.

(v) Adjustment of provision to be noted in the Appropriation (Votes) Ledgers: In order to ensure that the authorized financial provision under the new Project, Object Class, or Item is not exceeded, the transfer of provision should be noted in the Appropriation (Votes) Ledgers after the necessary authority for such transfer has been granted.

F.R. 69. Excess without prior authority.

(1) Under a Programme - If a Programme is exceeded without prior authority obtained before the 31st December of the Financial year, it should be reflected in the Appropriation Account and treated as an unauthorized excess on the Programme. Such excess will be examined by the Committee on Public Accounts. When the Committee on Public Accounts have reported that any excess has been incurred on a Programme and they have examined such excess, a resolution should be passed in Parliament to make good such Excess not later than 31st December of the year next but one after that to which the Excess relates.

(2) Under a Project, Object Class, or a Controlled Item detected during the financial year. Requisite authority for exceeding the provision under a Project, Object Class, or Controlled Item should invariably be obtained before the excess expenditure is actually incurred. If, however, an excess on a Project, Object Class, or a Controlled Item is detected after it has occurred, without prior authority, covering authority under the virement procedure may be granted by the appropriate authority, during the course of the financial year, provided it is satisfied with the reasons adduced for the failure to obtain prior authority.

(3) Under a Project, Object Class, or controlled Item detected after the end of the financial year, but before the Treasury Books are closed. The following procedure should be followed in dealing with such excesses:

(a) Transfer of provision between items of the same Object Class of a recurrent expenditure Project should be authorized by the Secretary to the Ministry concerned/Chief Accounting Officer.

(b) All other applications to cover excesses should be forwarded to the Treasury.

(c) Covering approval for such excesses can be granted by the appropriate authority only provided that –

(i) satisfactory reasons are adduced for not obtaining prior authority; (ii) savings are available under the Project; and (iii) the requirements in F.R.65 are satisfied.

(4) Under a Project, Object Class, or Controlled Item detected after the Treasury Books are closed. If the excesses is detected after the Treasury books are closed, it should be reflected in the Appropriation Accounts and will be treated as an Unauthorised Excess.

(5) Applications for covering authority envisaged in this Regulation should be made sextuplicate on Form General 233.

F.R.70 Creation of posts may be done following the procedure laid down in F.R. 71. No posts shall be created with retrospective effect extended back to lapsed financial years.

F.R.71. Posts, Cadre, Scales of Salary, etc.

(1) Whatever the source of provision or funds from which the staff involved is paid, the following matters require the prior authority of the Secretary to the Treasury or the Deputy Secretary to the Treasury who will obtain the concurrence of the Secretary to the Ministry in charge of the subject of Public Administration:

(a) Change of designation of posts, (b) creation of new posts, (c) grading of posts, (d) additions to authorized cadre,

(e) creation of new rates or scales of salary, wages, allowances and other emoluments and remuneration (e.g., fees), or (alterations to already approved) revision of existing rates or scales, (f) absorption of temporary employees into the permanent cadre.

(2) No change relating to the above matters should be introduced into the Draft Estimates of the department without the requisite authority.

(3) Authority obtained under (1) above can be given effect to only if appropriate financial provision is available under the votes of the Ministry/Department concerned.

(4) Such authority should be intimated with copies to the Secretary, Ministry of Public Administration and Auditor-General. Note 1. The form at Appendix 1.2. should be used for creation of new posts. Note 2. See F.R.238 (1). Note 3. Authority for the engagement of employees on a casual basis, under specific Conditions, exists in F.R.95

F.R.72 Revision of Total Cost Estimates

(1) The total Cost Estimates of any project (see F.R.20) shall not be exceeded during the financial year without authority in terms of (2) below. Departments should apply for the necessary authority as soon as an increase in cost is anticipated.

(2) When it is found that the Total Cost Estimates of a Work will be exceeded, authority should be obtained as follows to increase the Total Cost Estimate:-

(a) an increase upto 10 per cent but not exceeding Rs.25,000 approval of the Head of the Department;

(b) an increase upto 20 per cent but not exceeding Rs.500,000 approval of the Chief Accounting Officer who is a Secretary to a Ministry;

(c) an increase upto 25 per cent but not exceeding Rs.2,500,000 approval of the Secretary to the Treasury or Deputy Secretary to the Treasury;

(d) an increase over 25 per cent but not exceeding Rs.2,500,000 approval of the Minister of Finance;

(e) an increase exceeding Rs.2,500,000 approval of the Cabinet. A comparative statement as indicated in Appendix 2 should accompany every application for authority to revise the Total Cost Estimate.

(3) Where provision for works appears under the votes of one Department, but the works are executed by another Department, action for obtaining approval under (2) above should be initiated by the Department in whose votes the provision appears.

F.R.73 Variation of Limits of Advance Accounts – The Limits specified in the Annual Estimates in respect of Advance Account Activities cannot be varied except in terms of the appropriation Act. See also F.R.503.

F.R.74.

(1) Application for Supplementary Provision on Supply Services. On unforeseen circumstances or on a direction of the Cabinet, it becomes necessary for a Head of Department to incur expenditure and – (i) the expenditure is on a service which does not fall within the ambit of any Programme/Project, under his control, or (ii) the expenditure, though it falls within the ambit of the Programme/Project, will cause an excess thereon which cannot be appropriately and fully covered by Virement procedure, the Head of the Department shall submit to the Secretary to the Ministry concerned a report indicating the nature and extent of the service, the total cost thereof, and the amount of additional financial provision required. The Secretary will then submit the report with his comments to his Minister. If the Minister considers that Supplementary Estimate should be presented, he shall obtain the approval of the Cabinet for the purpose and thereafter direct the Secretary to prepare a resolution for submission to Parliament.

(2) Particulars to be furnished. When the proposed Supplementary Estimate is in respect of an existing Programme, the Head of the Department should specifically report whether –

(i) additional financial provision is required to the full extent of the additional expenditure; or

(ii) part of the additional expenditure can be met from savings. The Supplementary Estimate should be framed accordingly. The Head of the Department should report at the same time whether any savings are available which cannot properly be utilized under Virement procedure, and give full reasons for such savings. Savings so reported should be left unspent.

(3) Action will be taken by the Secretary to forward to Parliament the requisitenumber of copies of the Supplementary Estimate along with the Motion attached to it. (See Appendix 3 for specimen Motion and Supplementary Estimate.) Note. - The passing of the Supplementary Estimate does not in itself provide complete authority for expenditure. A Special Warrant should be issued – see F.R.90.

F.R.75. Form of Supplementary Estimate. The net amount of a Supplementary estimate shall be the amount of additional financial provision required less saving available for transfer.

F.R.76. Subsequent action on savings reported. Savings which have been indicated in a Supplementary Estimate, should be transferred under Virement procedure to the Object Class on which Supplementary Provision has been obtained.

F.R. 77. Special Law Service.

(a) Special Law Service not provided for in the annual Estimates in terms of F.R.19 When a service authorized by Law (other than the Appropriation Act) is not provided for in the Annual Estimate in terms of F.R.19, expenditure cannot be incurred thereon, unless a Warrant is issued under the hand of the Minister of Finance. The warrant for this purpose is issued on Form treasury 77. Application for such issue should be made through the Chief Accounting Officer, to the Secretary to the Treasury.

Additional Provision for Special Law Services. When additional provision is required under an existing Special Law Service provided for in the Annual Estimates, a Warrant under the hand of the Minister of Finance on Form Treasury 77 should be obtained.

F.R.78 Contingencies Fund.

(a) Article 151 of the Constitution reads as follows: “(1) Notwithstanding any of the provisions of Article 149, Parliament may by law create a Contingencies Fund for the purpose of providing for urgent and unforeseen expenditure.

(2) The Minister in charge of the subject of Finance, if satisfied -

(3) As soon as possible after every such advance, a Supplementary Estimate shall be presented to Parliament for the purpose of replacing the amount so advanced.”

(b) This implies that an application for an advance from the Contingencies Fund is appropriate only when - (i) the money is required for urgent and unforeseen expenditure for which no provision exists; (ii) the money cannot be found by Virement procedure, either because it is in appropriate or savings are not available; (iii) there is not sufficient time to apply for supplementary provision.

(c) On receiving the concurrence of the President, the Treasury will submit a Contingencies Fund Advance Warrant for the signature of the Minister of Finance. (see F.R.90 (2) ). This authority will be communicated by the Treasury to the departments concerned.

(d) The Contingencies Fund is a continuing one and does not lapse at the end of the financial year. All moneys taken from the fund should be repaid to it as early as possible in the same or the following financial year, by Supplementary Estimates.

(e) In the Supplementary Estimate presented to Parliament for this purpose, provision should be made for –

(i) the full amount of the advance obtained from the Contingencies Fund, and (ii) the amount necessary for further expenditure on the same service during the rest of the Financial Year in which the Supplementary Estimate is presented. In addition there should be a note, for purposes of information, indicating the amount of expenditure incurred out of the advance up to the time of presenting the Supplementary Estimate. See Appendix 4 for Specimen Motion and Supplementary Estimate.

(f) As regards accounting for Contingencies Fund Advance, see

F.R.487.

F.R.79 Copies of Authorities for variations to Estimates of Expenditure. Copies of authorities under this Section should be sent as follows:

(i) One copy each to the Accounting Officer and Chief Accounting Officer concerned. (ii) Two copies to the Auditor general and one copy to he Director-General of National Budget) of each authority under F.RR 66,68,69,71,72, 73, 74,77 and 78. (iii) One copy of each authority under F.RR. 66.68, 69, 73, 74, 77 & 78 to the Treasury (Director – General of State Accounts.)

(No. F.RR Issued Under Nos.80 and 81)

Section 6 — Estimates of Revenue

Section 6 – Estimates of Revenue

F.R.82 Revenue. For the purpose of the Estimates of Revenue, Revenue means and includes the gross receipts including reimbursements, less refunds by Government, other than those derived from following:- (i) receipt of Advance Account Activities, other than profits; (ii) loans and borrowings; (iii) receipts from the sale of investments, other than profits; (iv) deposits; (v) settlements of authorized advances; (vi) imprests and remittances; (vii) receipts of funds constituted by Special law permitted to exist outside the Consolidated Fund; (viii) credits to “Surcharge Account” as provided for in F.R.170 (3).

F.R. 83 Form of Annual Estimates of Revenue.

(1) Heads. – Revenue will be classified under the following Heads:- Head 1. Taxes on Production and Expenditure. Head 2. Taxes on Corporate Income. Head 3. Taxes from Non-Corporate Income. Head 4. Receipts of Trading Enterprises. Head 5. Rents, Interest, Profits and Dividends Received. Head 6. Sales and Charges. Head 7. Social Security Contributions. Head 8. Other Current Transfers. Head 9. Sales of Capital Goods. Head 10. Capital transfers from Domestic Sector. Head 11. Capital Transfers from Abroad. Head 12. Repayment of Loans and Advances. Head 13. Direct Borrowings from Domestic Sector. Head 14. Direct Borrowings from Foreign Sector Head 15. Cash Adjustments.

(2) Sub-heads, Items and sub-Items – Each Revenue Head is divided into Subheads, Items and Sub-Items as may be prescribed by the Secretary to the Treasury. The classification appearing in the Estimates of the current year shall be taken to be the prescribed form and will remain in force until it is amended by the Secretary to the Treasury.

(3) Arrears . – There should be no separate Head of Revenue for “Arrears of Revenue”. Arrears, short – collections, and any interest received thereon should be credited to the same Head, Sub-head, Item, and Sub-Item of Revenue on which they accrued.

F.R.84. Stamp Duties. Stamp duties should not form a separate Head of Revenue. Stamps sold for all purposes will, in the first instance, be brought to account under Sub – Item 1 “Stamps including composition duties other than for postal and court purposes” of Head 1, Sub-head 7. The Treasury will transfer from this Sub Item at the end or during the course of each financial year, amounts representing –

(a) the stamps used for postal purposes to Head 4 “Receipts of Trading Enterprises”, Sub-head 2, Item 1 “Postal”;

(b) stamps used for Court purposes (excluding stamps used for Fiscal’s processes) to Head 6, “Sales and Charges,” Sub-head 2, Item 2, “Court Fees”;

(c ) stamps used for other purposes, to the appropriate Heads, sub-heads, Items and Sub-heads, Items and Sub-Items of Revenue. Note. – In this connection see also F.R. 494.

F.R.85 (1) Preparation of Estimates of Revenue. – (a) Revenue Accounting officers should forward to the respective Chief Accounting Officers, on forms prescribed by the Treasury, not later than the 1st June of each year –

(i) a revised estimate of Revenue for the current financial year; (ii)an estimate of Revenue for the ensuing financial year based on the assumption that no change will be made in existing taxation and charges. Note. – 1. where the estimated Revenue is less than the anticipated gross receipts, the latter should be indicated by suitable foot – notes. Note. – 2. When the same type of Revenue is collected by a number of Accounting Officers, working under Chief Accounting Officer, the latter will be responsible for furnishing the Estimates of Revenue.

(b) Revenue Accounting Officer should take particular care to give all useful and relevant information relating to any increase or decrease of Revenue. Clear explanations should be given in respect of -

(i) any difference between the original and revised estimates for the current financial year; (ii) any difference between the revised estimate for the current financial year and the estimate for the next financial year; (iii) any marked difference between the actual Revenue for the last year for which the accounts have been closed, and revised estimate for the current financial year and the estimate for the ensuing year.

(c) Revenue Accounting Officers should also endeavour to make their estimates as realistic and accurate as possible.

(2) Forwarding of Revenue Estimates to Treasury.

(a) The Chief Accounting Officer will examine the estimates forwarded by the Revenue Accounting Officer and will forward them to the Director – General of Economic Affairs and Fiscal Policy not later than the 1st July of each year.

(b) If it is found necessary to vary the estimates subsequently, such variations should be reported to the Director-General of Economic Affairs and Fiscal Policy by the Chief Accounting Officer, with the reasons therefore.