**F.R. 65**. (1) The Annual Estimates of Expenditure approved by Parliament along with the Appropriation Act and Estimates of Expenditure approved by resolution passed in Parliament must be regarded as prescribing within hard and fast limits the purposes and the sums for which the provision prescribed may be spent, the cadre which maybe employed, and the total cost of particular projects. The specific purposes and the sums provided under the Heads, Programmes, Projects, Objects, Items and Financing details should not be varied without appropriate authority.

(2) Authority exists, under certain circumstances -

(i) to transfer any sum that has been allocated by appropriation Act to recurrent expenditure of any Programme appearing under any Head specified in the Annual Estimates of Expenditure, but has not been expended or is not likely to be expended, to Capital Component of another Programme under the same Head of Expenditure. (ii) to transfer savings from Projects standardized Object Classes, Items or Financing Details to other Projects, standardized Objects Classes, Items of Financing details of the same Programme (see F.R. 66) (iii)to create a new Project a standard Object class, an Item or a Financing detail ( see F.R. 68). (iv) to withdraw in whole, or in part, any amount previously released for expenditure (in accordance with the provisions of the Appropriation Act).

(v) to approve variations in the Cadre of an establishment and the alteration of Salary Scales etc, ( F.R. 71). (vi) to approve variations in the Total Cost Estimate of a Project or work (see F.R. 72). (vii) to approve increases in Heads of Expenditure – ( see F.R. 74) (viii) to vary the prescribed limits of Advance Accounts - ( see F.R. 73) (3) Virement Procedure: - Transfer of savings in the manner referred to in FR 65(2) (i), (ii) & (iii) above and FR 69 is generally referred to as “ Virement” Procedure.

(4) When Virement is not appropriate. - Virement Procedure cannot, and should not be adopted -

(j) to transfer savings in a Head of Expenditure to another Head of Expenditure. (ii) to transfer savings in a provision for Capital Expenditure to Recurrent Expenditure of the same Programme or to Recurrent or Capital Expenditure of another Programme under the same Head. (iii) to transfer savings from a Special Law provision to a Appropriation Law provision ( Supply Service), between Special Law Service provisions or from Appropriation Law provision to a Special Law provision. (iv)to create a project, Standard Object, Item or Financing detail for a new Special Law Service unless authorized by Law passed in Parliament.

(v) to transfer savings in a provision if it involves:-

(a) transfer of Savings from any Foreign Aid Financing Detail to Consolidated Fund Financing Detail.

(b) transfer to savings from a direct Foreign Aid Financing Detail to a Reimbursable Foreign Aid Financing Detail or to a counterpart Funds Financing Detail.

(c) Transfer of savings from a Counterpart Fund Financing Detail to a Consolidated Fund Financing Detail. (vi) to create or increase or transfer savings from provision for grants or subsidies to any specific institution, agency or individual (F.R. 18) (vii) to transfer savings from provision made for covering up of losses in the Working of Advance Account Activities. (viii) If the additional or new expenditure envisaged is not approved by the appropriate authority and involves a drastic change in the scale of operations from that presented in the approved Estimates; or if the proposed new service is one which there is reason to believe, Parliament would wish to consider in advance; or if such service will commit the Government to expenditure of large sums of money in the future years. (ix) Unless the savings indicated are definitely available; or anticipated beyond reasonable doubt.

(x) If the savings arise through postponement of a project appearing in the Estimates approved by Parliament and can be implemented in the course of the Financial year. (xi) to transfer savings from provision made under a Supplementary Estimate or other Resolution. (xii) in violation of any other restriction imposed by footnotes in the printed Estimates. (xiii) in violation of any other specific restriction imposed by Treasury circulars or otherwise. (xiv) If the transfer is from or between the Object Codes in the Rehabilitation and Improvements of Capital Assets Object Category.

(5) Changed of Legend:

(a) Change in the legend or title of a Programme would not be allowed during a Financial year.

(b) Change in the legend or title of a Project would not be allowed if it is not approved by the proper authority or if it involves radical change in the objectives or policy relating to the project. Only changes necessary for technical reasons or correction of errors would be approved. All Amendments of Legends should be specifically approved by the Secretary to the Treasury, Deputy Secretary to the Treasury or by an officer authorized by the Secretary to the Treasury.

(c) Changes in the legends of the standardized “Object Classes” of expenditure would not be permitted.

(d) The amendments in a Financing Detail of a Project would not be permitted unless there are technical reasons to do so or there is an error. All such amendments should be authorized by the Secretary to the Treasury, Deputy Secretary to the Treasury or by an officer authorized by Secretary to the Treasury.