F.R.4 — F.R.4 The Programming of Expenditure.** (1) It is the responsibility of the Chief Accounting Officer and the Accounting Officer to ensure that the funds

fr-4 · regulation · Chapter 1 — Estimates Of Expenditure And Revenue · PDF p.15 · folio 9-10 · corpus 2026-11-07b

**F.R.4 The Programming of Expenditure.** (1) It is the responsibility of the Chief Accounting Officer and the Accounting Officer to ensure that the funds to be authorized by Parliament in the Annual Estimates is restricted to the programme of work that can be achieved during the financial year.

(2) The Programming for Implementation should normally be done when projects are formulated. In any case it should be done before the financial year of expenditure commences. No financial commitment or liability should be incurred until the relevant warrant is issued. ( see FR 90) (3) Feasibility studies regarding recurrent expenditure should be under-taken and expenditure forecasted before budgeting. Targets, output and objectives of recurrent expenditure should clearly be defined to restrain undue expansion of expenditure. Ways and means of eliminating waste and effecting strict economics should be adopted. Organization should be structured to ensure closer monitoring and accountability. For this purpose each project and object class may be divided into suitable smaller units or components.

(4) When the capital projects are duly approved, the implementing agency should prepare the detailed Total Cost Estimate indicating the sources of financing and also draw up a programme of implementation indicating the time span. Each project and object class may be broken into items, works, tasks, activities or any other convenient cost units to facilitate monitoring and progress control. A suitable technique like the Network Analysis may be used for the implementation programme.

(5) A Progress/Monitoring committee should be set up in each implementing agency to ensure that the output is achieved as programmed. For this purpose, the committee should among other things:-

(a) maintain a detailed breakdown of the projects into items of work, tasks, activities etc.

(b) record progress according to predetermined target dates.

(c) Attempt to identify constraints relating to materials, personnel or organization which may delay progress and take timely remedial action. The progressive compilation of work-norms and the formulation of units costs will also be an important part of the Committee’s duties. The committee shall report regularly to the Accounting Officer and the Chief Accounting Officer. When other departments are involved in the completion of particular aspects of departmental projects, officers of such other departments may also be co-opted as members of the Committee. This should be done in consultation with the Secretaries concerned.

(6) The Chief Accounting Officer should exercise general supervision over the detailed programming of expenditure and should wherever necessary, co-ordinate the activities of the several departments under his control.