**F.R. 36. Final Approval**. (1) Sectoral Plans or Programmes and Large Projects should receive Final Approval. Final Approval for all large Projects is necessary before –
(a) the Project can be listed as “ accepted” in the Public Investment Programme.
(b) it can appear in the Government Budget and have funds made available for implementation whether from domestic or foreign sources.
(c) final negotiations between the Director of External Resources with prospective donors for the conclusion of an aid agreement can take place.
(2) Large Projects are of two types namely -
(a) Commercial Projects - Commercial Projects are projects which will produce output of goods or services which will be sold at market prices. These will include any projects for manufacturing industrial goods or growing agricultural produce. Most of such projects are executed either through Advance Account Activities (see F.R. 15) or by Public Corporations.
(b) Non-Commercial Projects - Non-Commercial Projects will generally include those projects which provide services to the public for which market prices are not charged. Such projects are found within the General framework of economic or Social Infrastructure or overheads. Certain projects in industry or agriculture, for example, research or extension projects would also fall into this category.
(3) When submitting large projects for final approval information should be supplied in the formats prescribed by the National Planning Department.
(4) On receipt of a request for the final approval the National Planning Department will prepare a report on the project and submit it to the committee of Development Secretaries.
(5) Once the project has received approval from the committee of Development Secretaries it will be forwarded to the Cabinet for further consideration. If considered feasible it will receive Final Approval and would be included in the Public Investment Programme.
**(No F.R. Issued Under 37)**